A decision by the governing bodies of the City of Santa Cruz (SCWD) and Soquel Creek Water District (SqCWD) for the construction of a 2.5 million gallon per day desalination facility is dependent upon the successful completion of the pilot test program, technical review of the data collected, and environmental approval and permitting of the proposed project.
Currently, the project is undergoing the environmental review process.
| Title | Dates |
|---|---|
| Pilot Plant Testing | March 2008 - April 2009 |
|
SWRO Desalination Facility
Environmental Impact Report Preparation & Certification |
2010 - 2012 |
| SWRO Desalination Facility Design | 2010 - 2012 |
| SWRO Desalination Facility Construction | 2012 - 2016 |
To view the schedule as a .pdf, click the image or click here.